COUNTY OF SAN MATEO
Inter-Departmental Correspondence
|
County Manager's Office
|
|
DATE:
|
Sept.11, 2001
|
BOARD MEETING DATE:
|
September 25, 2001
|
|
TO:
|
Honorable Board of Supervisors
|
FROM:
|
Paul T. Scannell, Assistant County Manager
|
SUBJECT:
|
Hall of Justice (HOJ) Remodel Project, Project Nos. P-3V01, P3V02, P3V03
|
Recommendation
Approve the following Revision Orders:
|
|
R.O.Number
1
|
Amount
$213,764
|
Contrator
Turner Construction Co.
|
|
Background
On Feb. 15, 2000, by Resolution No. 63409, the Board of Supervisors approved revisions of the HOJ Remodel Project: new offices and Courtroom for Family Court Services, 6th Floor, and renovations to the District Attorney's offices, 3rd Floor, and approved bids in the amount of $ 2,187,590 for construction. The contract includes a separate component for Turner Construction Co. (TCC) in the amount of $524,948. Final changes to the construction costs resulting from County-initiated changes and unforeseen conditions have been approved and a final closeout of the project has been prepared for Board approval. Terms of the Contract provide that the approved amount for the Trade Contractors is to be supplemented by a fee for TCC based on the cost of the changes.
|
|
Discussion
Revision Order No. 1 includes additional trade contract costs to the following trade contractors in the total amount of $182,704. Additional TCC fees for this additional work based on the total amount is $31,060
|
|
Fiscal Impact
Revision Order No.1
$182,704 + $31,060
|
|
Grand Total Revision Order No. 1
$213,764
|
|
Contractor
|
RO
|
Original Contract
|
Prior Revisions
|
This Revision
|
Revised Contract
|
|
TCC
|
1
|
$2,712,538
|
$0
|
$213,764
|
$2,926,302
|
|
Funding Source:
Each participating department in this contract is funding its portion of the Project Costs and the General Fund Amount of $45,572 is being funded by Non- Departmental Reserves
|