REVISION ORDER BREAKDOWN
PROJECT: San Mateo County Health Center, '54 Building Remodel
PROJECT NO.: P1701
CONTRACTOR: Turner Construction Company
REV. ORDER NO.: 5
DATE: April 15, 2002
Description |
Change |
Amount | |
1. |
COR 017, PI5039 - Window refurbishing |
Add |
$45,357 |
2. |
COR 019, PI5014 - 3rd Floor Doctor's office remodel |
Add |
220,241 |
3. |
COR 020, PI5037 - Amerinet member credit |
Deduct |
-3,967 |
4. |
COR 021, PI5032- Revise Private Dining Room layout |
Add |
18,658 |
5. |
COR 022, PI5016 - Revise Security Locker Room layout |
Add |
10,681 |
6. |
COR 023, PI5051 - Change communications racks |
Add |
501 |
TOTAL |
$291,471 |