|
|
|
|
|
|
|

|
COUNTY OF SAN MATEOInter-Departmental Correspondence |
Department of Public Works |
|
DATE: |
April 18, 2002 |
BOARD MEETING DATE: |
May 7, 2002 |
|
TO: |
Honorable Board of Supervisors |
FROM: |
Neil R. Cullen, Director of Public Works |
SUBJECT: |
Emerald Lake Hills Resurfacing Project - Redwood City Area (County Project No. R7W00 - F36 [369]) |
|
Recommendation |
Adopt a resolution awarding and authorizing execution of a contract for resurfacing of various roads within Emerald Lake Hills. |
|
Previous Board Action |
Adopted Resolution No. 65126 on March 19, 2002, adopting Plans and Specifications, determining prevailing wage scales, and calling for sealed proposals for the above referenced project. |
|
Discussion |
On April 16, 2002, bids were accepted for this project and subsequently referred to this office for checking and recommendation. The bids have been checked and the bid of: |
|
Interstate Grading & Paving, Inc. |
128 South Maple Ave. P.O. Box 389 |
South San Francisco, California 94080 |
|
at $271,253 was the lowest bid received. The Engineer's estimate was $330,000. A summary of the bids received is as follows: |
|
|
1. |
Interstate Grading & Paving, Inc. |
$271,253.00 |
|
|
2. |
McGuire & Hester |
$298,246.00 |
|
|
3. |
O'Grady Paving, Inc. |
$299,126.00 |
|
|
4. |
Granite Rock Company dba Pavex Construction |
$299,485.00 |
|
|
5. |
C.F. Archibald Paving, Inc. |
$299,552.80 |
|
|
6. |
G. Bortolotto & Co., Inc. |
$348,841.31 |
|
|
7. |
Half Moon Bay Grading & Paving, Inc. |
$356,335.00 |
|
|
We have reviewed the contract documents and have determined that the affirmative action program of Interstate Grading & Paving, Inc. is in accordance with the current Affirmative Action Guidelines. |
|
Vision Alignment |
We believe our recommendation is consistent with the Shared Commitment to "Ensure Basic Health and Safety for All" and Goal Number 7 "Maintain and Enhance the Public Safety of All Residents and Visitors," as it improves the conditions of these roads for the public's safety. |
|
Fiscal Impact |
The total estimated cost of construction and contingencies is $298,000, which includes a ten percent (10%) contingency as the work is bid on a unit price basis (i.e., ton of asphalt placed, square yard of pavement fabric, etc.). The contingency is used to pay the contractor for any additional material placed as the actual tonnage used depends on the unit weight of the asphalt and the tolerances for the actual thickness of the pavement placed. |
|
Funds have been appropriated in the Road Fund to finance this work. There is no impact to the General Fund. |
|
A form of resolution has been approved by County Counsel. |