REVISION ORDER BREAKDOWN

PROJECT: San Mateo County Health Center, '54 Building Remodel

PROJECT NO.: P1701

CONTRACTOR: Turner Construction Company

REV. ORDER NO.: 6

DATE: May 6, 2002

 

Description

Change

Amount

1.

COR 018, PI5011A - Revised Medical Records layout

Add

$20,729

2.

COR 028, PI5012 - Painting allowance

Deduct

-48,349

3.

COR 024, PI5028 - Delete tile wall at surgery area

Add

4,056

4.

COR 003, PI5029 - Additional cable for PBX

Add

4,096

5.

COR 015, PI5045 - Relocate communications ladder racks

Add

738

6.

COR 027, PI5047 - Add 30 amp circuits

Add

3,402

7.

COR 025, PI5056 - Restrooms sound insulation

Add

2,490

8.

COR 026, PI5060 - Cardkey software for remote server

Add

3,059

9.

COR 016, PI5066 - Tube steel supports at 3rd Floor link

Add

7,612

 

TOTAL

DEDUCT

-$2,167

BOS206ro6breakdownTurner