REVISION ORDER
Project: '54 Building Remodel |
Project No. P1701 |
San Mateo County Health Center |
Revision Order No. 6 |
San Mateo County, California |
Contract Resolution No. 64828 |
Contractor: TURNER CONSTRUCTION COMPANY
________________________________________________________________________
As provided by the General Conditions of the Agreement, this Revision Order constitutes full and final adjustment of the Contract Amount and Contract Time in compensation for the changes to the Work described herein. No claim for time or money relating to this Revision Order, including the changed Work or the impact of changes on the Project, will be allowed after execution of this document. Unchanged portions of the Agreement remain in full force and effect.
________________________________________________________________________
Change to the Work: See attached Revision Order Breakdown which is incorporated herein as if fully set forth.
Contract Summary |
|
Original Contract Amount |
$1,037,404.00 |
Former Revisions |
8,407,119.49 |
Net Amount Prior to This Revision |
9,444,523,49 |
THIS REVISION ORDER |
-2,167.00 |
Revised Contract Amount |
$9,442,356.49 |
The Contract completion date is October 13, 2002.
Approvals
CONSTRUCTION MANAGER: |
OWNER: | |
TURNER CONSTRUCTION CO. |
COUNTY OF SAN MATEO | |
Signed by:_____________________________ |
Signed by:___________________________ | |
Date: ________________________________ |
Date:________________________________ |
BOS206ro6Turner