COUNTY OF SAN MATEO

Inter-Departmental Correspondence

Department of Public Works

DATE:

May 31, 2002

   

BOARD MEETING DATE:

June 18, 2002

 

TO:

Honorable Board of Supervisors

FROM:

Neil R. Cullen, Director of Public Works

SUBJECT:

Resurfacing of Alameda de las Pulgas from Woodside Road to Stockbridge Avenue, Federal Project Number STPL-5935 (017) 04-SM-0-CR

 

Recommendation

Adopt a resolution awarding and authorizing execution of a contract for the resurfacing of portions of Alameda de las Pulgas between Woodside Road and Stockbridge Avenue.

 

Previous Board Action

Adopted Resolution No. 65221 on April 30, 2002, adopting Plans and Specifications, determining prevailing wage scales, and calling for sealed proposals for the above referenced project.

 

Key Facts

We have received a grant made available through the Federal Surface Transportation Program to partially finance the project.

   

Discussion

On May 28, 2002, bids were accepted for this project and subsequently referred to this office for checking and recommendation. The bids have been checked and the bid of:

 

G. Bortolotto & Co., Inc.

580 Bragato Road

San Carlos, CA 94070-6227

 

at $159,853.70, was the lowest bid received.

 

The Engineer's estimate was $227,000. A summary of the bids received is as follows:

 
 

1.

G. Bortolotto & Co., Inc.

$159,853.70

 

2.

Redgwick Construction Co.

$159,949.00

 

3.

Interstate Grading and Paving

$174,823.90

 

4.

McGuire & Hester

$174,857.00

 

5.

C.F. Archibald Paving, Inc.

$182,037.00

 

6.

O'Grady Paving, Inc.

$189,342.45

 

7.

Pavex Construction/Granite Rock Co.

$209,900.00

 

We have reviewed the contract documents and have determined the Affirmative Action Program submitted by G. Bortolotto & Co., Inc. is in accordance with the current Affirmative Action Guidelines.

 

Vision Alignment

We believe our recommendation is consistent with the Shared Commitment to "Ensure basic health and safety for all" and Goal Number 7, "Maintain and enhance public safety of all residents and visitors," as it will improve the conditions of the road surface for benefit of the public.

 

Fiscal Impact

The total overall estimated cost of this project, including construction and contingencies is $176,000, which includes a ten percent (10%) contingency as the work is bid on a unit price basis (i.e., ton of asphalt placed, square yard of pavement repair, etc.). The contingency is used to pay the contractor for any additional material placed as the actual tonnage used depends on the unit weight of the asphalt and the tolerances for the actual thickness of the pavement placed.

 

The project is proposed to be financed with Road Funds that were appropriated in the 2001-02 Budget.

 

The Road Fund will be reimbursed with $60,000 in Federal Grant Funds once the project is complete.

 

There is no impact to the General Fund.

 

A form of Resolution has been approved by County Counsel.