REVISION ORDER BREAKDOWN
PROJECT: San Mateo County Health Center, '54 Building Remodel
PROJECT NO.: P1701
CONTRACTOR: Turner Construction Company
REV. ORDER NO.: 7
DATE: June 3, 2002
Description |
Change |
Amount | |
1. |
COR 005, PI5036 - Code Blue Nursecall upgrade |
Add |
$12,720 |
2. |
COR 037, PI5053 - Add Cardkey to PBX |
Add |
3,535 |
3. |
COR 032, PI5054 - Computer Training Room telephone |
Add |
217 |
4. |
COR 033, PI5065 - Demo furred walls in Security |
Add |
7,845 |
5. |
COR 030, PI5068 - Cap steam leak in cafeteria |
Add |
3,231 |
6. |
COR 034, PI5072 - Enlarge Linen Room door |
Add |
2,623 |
7. |
Bid Package 3 - Landscape/Irrigation (Shooter and Butts, Inc.) |
Add |
68,436 |
BP3 - Construction Management Fee 5% |
Add |
3,422 | |
BP3 - Construction Contingency 7% |
Add |
4,791 | |
TOTAL |
ADD |
$106,820 |