COUNTY OF SAN MATEO Inter-Departmental Correspondence | ||||||
Department of Public Works | ||||||
DATE: |
July 19, 2002 | |||||
BOARD MEETING DATE: |
July 30, 2002 | |||||
TO: |
Honorable Board of Supervisors | |||||
FROM: |
Neil R. Cullen, Director of Public Works | |||||
SUBJECT: |
Cape Sealing of Various Roads - Skyline Area (County Project No. R8T00 - F36 [212A]) | |||||
Recommendation | ||||||
Adopt a resolution awarding and authorizing execution of a contract for the Cape Sealing of Various Roads within the Skyline Area. | ||||||
Previous Board Action | ||||||
Adopted Resolution No. 65399 on June 25, 2002, adopting Plans and Specifications, determining prevailing wage scales, and calling for sealed proposals for the above referenced project. | ||||||
Discussion | ||||||
On July 16, 2002, bids were accepted for this project and subsequently referred to this office for checking and recommendation. The bids have been checked and the bid of: | ||||||
Western States Surfacing, Inc. | ||||||
1601 Culpepper Avenue | ||||||
Modesto, CA 95351 | ||||||
at $273,258.19 was the lowest bid received. The Engineer's estimate was $275,000. A summary of the bids received is as follows: | ||||||
1. |
Western States Surfacing, Inc. |
$273,258.19 |
||||
2. |
Intermountain Slurry Seal, Inc. |
$277,165.00 |
||||
3. |
American Asphalt Repair |
$320,222.00 |
||||
4. |
California Pavement Maintenance Co. |
$323,450.00 |
||||
5. |
Franklin Construction |
$363,500.00 |
||||
6. |
Graham Contractors |
$367,150.00 |
||||
We have reviewed the contract documents and have determined that the affirmative action program of Western States Surfacing, Inc. is in accordance with the current Affirmative Action Guidelines. | ||||||
Vision Alignment | ||||||
We believe our recommendation is consistent with the Shared Commitment to "ensure basic health and safety for all" and Goal Number 7 "maintain and enhance the public safety of all residents and visitors," as it improves the conditions of the roads' surface for the benefit of the public. | ||||||
Fiscal Impact | ||||||
The total estimated cost of construction and contingencies is $301,000, which includes a ten percent (10%) contingency as the work is bid on a unit price basis (i.e., square yard of cape seal and pavement repair, etc.). The contingency is used to pay the contractor for any additional cape seal or pavement repair areas that may be required at the time of construction. | ||||||
Funds have been appropriated in the Road Fund to finance this work. There is no impact to the General Fund. | ||||||
A form of resolution has been approved by County Counsel. |