REVISION ORDER BREAKDOWN

PROJECT: San Mateo County Health Center, '54 Building Remodel

PROJECT NO.: P1701

CONTRACTOR: Turner Construction Company

REV. ORDER NO.: 9

DATE: July 22, 2002

 

Description

Change

Amount

1.

COR 047, PI 5029B - Replace B-line racks in TC1

Add

$1,291

2.

COR 036, PI 5059 - Add Cardkey to HIT

Add

6,759

3.

COR 031, PI 5069 - Add locking hardware on closets

Add

2,655

4.

COR 049, PI5071 - Illuminated sign at west loading dock

Add

10,551

5.

COR 056, PI5083 - Cafeteria remodel and fire sprinkling

Add

180,838

6.

COR 046, PI 5084 - Equipment rack at TC2.0

Add

1,293

7.

COR 050, PI5086 - 3rd Floor link concrete wall

Add

15,656

8.

COR 053, PI5087 - Room 268 plaster demo

Add

4,246

9.

COR 048, PI5089 - Relocate 3rd Floor air plenums above ceiling

Add

10,000

10.

COR 052, PI5090 - Add outlets in ISD

Add

913

11.

COR 051, PI5091 - Add outlet for Materials Management

Add

426

 

TOTAL

ADD

$234,628