REVISION ORDER BREAKDOWN
PROJECT: San Mateo County Health Center, '54 Building Remodel
PROJECT NO.: P1701
CONTRACTOR: Turner Construction Company
REV. ORDER NO.: 9
DATE: July 22, 2002
Description |
Change |
Amount | |
1. |
COR 047, PI 5029B - Replace B-line racks in TC1 |
Add |
$1,291 |
2. |
COR 036, PI 5059 - Add Cardkey to HIT |
Add |
6,759 |
3. |
COR 031, PI 5069 - Add locking hardware on closets |
Add |
2,655 |
4. |
COR 049, PI5071 - Illuminated sign at west loading dock |
Add |
10,551 |
5. |
COR 056, PI5083 - Cafeteria remodel and fire sprinkling |
Add |
180,838 |
6. |
COR 046, PI 5084 - Equipment rack at TC2.0 |
Add |
1,293 |
7. |
COR 050, PI5086 - 3rd Floor link concrete wall |
Add |
15,656 |
8. |
COR 053, PI5087 - Room 268 plaster demo |
Add |
4,246 |
9. |
COR 048, PI5089 - Relocate 3rd Floor air plenums above ceiling |
Add |
10,000 |
10. |
COR 052, PI5090 - Add outlets in ISD |
Add |
913 |
11. |
COR 051, PI5091 - Add outlet for Materials Management |
Add |
426 |
TOTAL |
ADD |
$234,628 |
BOS209ro9breakdownTurner