COUNTY OF SAN MATEO Inter-Departmental Correspondence | ||||||
Department of Public Works | ||||||
DATE: |
August 1, 2002 | |||||
BOARD MEETING DATE: |
August 20, 2002 | |||||
TO: |
Honorable Board of Supervisors | |||||
FROM: |
Neil R. Cullen, Director of Public Works | |||||
SUBJECT: |
Pescadero Creek Road Resurfacing - La Honda Area (County Project No. R5F00 - F 131 [17A]) | |||||
Recommendation | ||||||
Adopt a resolution awarding and authorizing execution of a contract for the resurfacing of a portion of Pescadero Creek Road. | ||||||
Previous Board Action | ||||||
Adopted Resolution No. 65431 on July 9, 2002, adopting plans and specifications, determining prevailing wage scales, and calling for sealed proposals for the above referenced project. | ||||||
Discussion | ||||||
On July 30, 2002, bids were accepted for this project and subsequently referred to this office for checking and recommendation. The bids have been checked and the bid of: | ||||||
Graniterock Co. dba Pavex Construction Division | ||||||
330 Blomquist Street | ||||||
Redwood City, CA 94063 | ||||||
at $265,828.00, was the lowest bid received. | ||||||
The Engineer's estimate was $322,000. A summary of the bids received is as follows: | ||||||
1. |
Graniterock Co. dba Pavex Construction Division |
$265,828.00 |
||||
2. |
Half Moon Bay Grading & Paving, Inc. |
$274,387.00 |
||||
3. |
C. F. Archibald Paving Inc. |
$277,994.20 |
||||
4. |
Interstate Grading & Paving, Inc. |
$279,991.50 |
||||
5. |
O'Grady Paving Inc. |
$291,825.00 |
||||
We have reviewed the contract documents and have determined the Affirmative Action Program submitted by Graniterock Co. dba Pavex Construction Division is in accordance with the current Affirmative Action Guidelines. | ||||||
Vision Alignment | ||||||
We believe our recommendation is consistent with the Shared Commitment to "ensure basic health and safety for all" and Goal Number 7, "maintain and enhance public safety of all residents and visitors," as it will improve the conditions of the road surface for the benefit of the public. | ||||||
Fiscal Impact | ||||||
The total overall estimated cost of this project, including construction and contingencies is $292,000, which includes a ten percent (10%) contingency as the work is bid on a unit price basis (i.e., ton of asphalt placed, square yard of pavement repair, etc.). The contingency is used to pay the contractor for any additional material placed as the actual tonnage used depends on the unit weight of the asphalt and the tolerances for the actual thickness of the pavement placed. | ||||||
There is no impact to the General Fund. | ||||||
A form of resolution has been approved by County Counsel. |