REVISION ORDER BREAKDOWN

PROJECT: San Mateo County Health Center, '54 Building Remodel

PROJECT NO.: P1701

CONTRACTOR: Turner Construction Company

REV. ORDER NO.: 10

DATE: August 26, 2002

 

Description

Change

Amount

1.

COR 057, PI 5048 - Replace light fixtures in TC1

Add

$1,026

2.

COR 055, PI 5070 - Add sheet metal parapet cap

Add

20,968

3.

COR 054, PI 5088 - Install wall to separate conference rooms

Add

7,059

4.

COR 058, PI 5107 - Deduct med gas panel from contract scope

Deduct

-7,613

 

TOTAL

ADD

$21,440

BOS210ro10breakdownTurner