REVISION ORDER BREAKDOWN
PROJECT: San Mateo County Health Center, '54 Building Remodel
PROJECT NO.: P1701
CONTRACTOR: Turner Construction Company
REV. ORDER NO.: 11
DATE: September 20, 2002
Description |
Change |
Amount | |
1. |
COR 066, PI 5094 - VCT flooring in Medical Records |
Add |
$660 |
2. |
COR 067, PI 5095 - Room 304 HVAC |
Add |
3,959 |
3. |
COR 068, PI 5097 - Admin Wing entrance glazing, HVAC |
Add |
1,079 |
4. |
COR 065, PI 5098 - Demo walls in Adm. Room 268, frame, sills |
Add |
19,906 |
5. |
COR 059, PI 5100 - Fire sprinkler credit in Cafeteria |
Deduct |
-15,199 |
6. |
COR 062, PI 5101 - Bumper guards in Linen |
Add |
1,965 |
7. |
COR 064, PI 5104 - Wire migration TC1 |
Add |
6,336 |
8. |
COR 071, PI 5015 - Deduct tackboards and markerboards |
Deduct |
-14,250 |
9. |
COR 060, PI 5108 - Conduit from fire control to telephone room |
Add |
470 |
10. |
COR 061, PI 5111 - Medical Records copier outlet |
Add |
590 |
11. |
COR 069, PI 5114 - Credit for Room 268 demo |
Deduct |
-3,992 |
12. |
COR 063, PI 5115 - Cap valve in dry storage |
Add |
704 |
13. |
COR 072, PI 5118 - 3rd Floor link tube steel revision |
Deduct |
-6,519 |
14. |
COR 070, PI 5119 - Spawled exterior plaster |
Add |
22,094 |
TOTAL |
ADD |
$17,803 |