REVISION ORDER BREAKDOWN
PROJECT: San Mateo County Health Center, '54 Building Remodel
PROJECT NO.: P1701
CONTRACTOR: Turner Construction Company
REV. ORDER NO.: 12
DATE: December 3, 2002
Description |
Change |
Amount | |
1. |
COR 081, PI 5093 - Rate of rise heat detector |
Add |
$2,081 |
2. |
COR 075, PI 5099 - Stagger corridor lights |
Add |
1,017 |
3. |
COR 074, PI 5116 - West entrance storefront upgrade |
Add |
6,214 |
4. |
COR 073, PI 5121 - Roof maintenance |
Add |
6,339 |
5. |
COR 076, PI 5122 - 3rd Floor fire alarm credit |
Deduct |
-11,000 |
6. |
COR 077, PI 5123 - Preconstruction extension |
Add |
47,859 |
7. |
COR 080, PI 5124 - Additional general liability insurance |
Add |
21,879 |
8. |
COR 079, PI 5125 - Replace 2nd Floor pan decking |
Add |
19,237 |
9. |
COR 078, PI 5126 - Additional field supervision |
Add |
20,207 |
10. |
COR 082, PI 5127 - Contingency savings participation |
Deduct |
-153,910 |
TOTAL DEDUCT |
-$40,077 |
BOS212ro12breakdownTurner