COUNTY OF SAN MATEO Inter-Departmental Correspondence | ||||||
Department of Public Works | ||||||
DATE: |
July 9, 2003 | |||||
BOARD MEETING DATE: |
July 15, 2003 | |||||
TO: |
Honorable Board of Supervisors | |||||
FROM: |
Neil R. Cullen, Director of Public Works | |||||
SUBJECT: |
Alameda de las Pulgas Streetscape Project from Ashton Avenue to near Harkins Avenue - West Menlo Park Area | |||||
Recommendation | ||||||
Adopt a resolution awarding and authorizing execution of a contract for the Alameda de las Pulgas Streetscape Project - West Menlo Park Area. | ||||||
Previous Board Action | ||||||
Adopted Resolution No. 060110 on June 10, 2003, adopting plans and specifications, determining prevailing wage scales, and calling for sealed proposals for the above referenced project. | ||||||
Discussion | ||||||
On July 8, 2003, bids were accepted for this project and subsequently referred to this office for checking and recommendation. The bids have been checked and the bid of: | ||||||
Golden Bay Construction, Inc. | ||||||
582 Bragato Road | ||||||
San Carlos, CA 94070-6227 | ||||||
at $440,348.24 was the lowest bid received. The Engineer's estimate was $434,000.00. A summary of the bids received is as follows: | ||||||
1. |
Golden Bay Construction, Inc. |
$ 440,348.24 |
||||
2. |
Esquivel Grading & Paving, Inc. |
$ 443,203.30 |
||||
3. |
Interstate Grading & Paving, Inc. |
$ 456,705.50 |
||||
4. |
Sposeto Engineering, Inc. |
$ 542,829.70 |
||||
5. |
J.W. Riley & Son, Inc. |
$ 583,860.10 |
* | |||
* Rejected - Equal Benefits section not completed | ||||||
We have reviewed the contract documents and have determined that the affirmative action program of Golden Bay Construction, Inc. is in accordance with the current Affirmative Action 12 Guidelines. | ||||||
Vision Alignment | ||||||
We believe our recommendation is consistent with the Shared Commitment to be a "responsive, effective and collaborative government" and Goal Number 20 "government decisions are based on careful consideration of future impact, rather than temporary relief or immediate gain," as the project complies with the direction given by your Board which provides for the current needs of the community as well as providing improvements that can be integrated into the redevelopment of the adjacent properties. | ||||||
Fiscal Impact | ||||||
The total estimated cost of construction and contingencies is $484,400, which includes a ten percent (10%) contingency (approximately $44,000) as the work is bid on a unit price basis (i.e., ton of asphalt placed, cubic yard of concrete, etc.). The contingency is used to pay the contractor for any additional material placed for the various bid items as the actual quantity used depends on the unit weights of the material and the actual limits of the as constructed project. Road funds will be used to finance road paving and striping work and Half Cent Transportation funds will be used to finance the remainder of the project. | ||||||
There is no impact to the General Fund. | ||||||
A form of resolution has been approved by County Counsel. |