COUNTY OF SAN MATEO

Inter-Departmental Correspondence

Department of Public Works

 

DATE:

July 2, 2004

BOARD MEETING DATE:

July 27, 2004

 

TO:

Honorable Board of Supervisors

FROM:

Neil R. Cullen, Director of Public Works

SUBJECT:

Reconstruction of 11th Avenue – North Fair Oaks Area
(Project No. RA600, F-36 [261A])

 

Recommendation

Adopt a resolution awarding and authorizing execution of a contract for the reconstruction of 11th Avenue.

 

Previous Board Action

Adopted Resolution No. 66709 on June 8, 2004, which adopted plans and specifications, determined prevailing wage scales and called for sealed proposals for the above-mentioned project.

 

Discussion

On Tuesday, June 29, 2004, bids were accepted for this project and subsequently referred to this office for checking and recommendation. The bids have been checked and the bid of:

 

Half Moon Bay Grading and Paving, Inc.

1780 Higgins Canyon Road

Half Moon Bay, CA 94019-2522

 

at $165,621 was the lowest bid received.

 

The Engineer’s estimate was $190,000. A summary of the bids received is as follows:

 
 

1.

Half Moon Bay Grading and Paving, Inc.

$165,621.00

 
 

2.

G. Bortolotto and Co.

$187,429.10

 
 

3.

O'Grady Paving, Inc.

$203,551.00

 
 

4.

Interstate Paving and Grading

$234,993.00

 
 

5.

C.F. Archibald Paving, Inc.

$239,930.00

 
 

6.

Pavex Construction (Granite Rock)

$286,125.00

 
 

We have reviewed the contract documents and have determined that the Affirmative Action Program submitted by Half Moon Bay Grading and Paving, Inc. is in accordance with the current Affirmative Action Guidelines.

 

Vision Alignment

We believe our recommendation is consistent with the Shared Commitment to “ensure basic health and safety for all” and Goal Number 7, “maintain and enhance public safety of all residents and visitors,” as it will improve the condition of the road surface for the benefit of the public.

 

Fiscal Impact

The total estimated cost for construction is $182,500, which includes a ten percent (10%) contingency (approximately $16,900) as the work is bid on a unit price basis (i.e., tons of asphalt concrete placed, cubic yards of concrete installed). The contingency is used to pay the contractor for any additional material placed for the various bid items as the actual quantity used depends on the unit weight and actual limits of the construction project.

 

Funds have been appropriated in the Road Fund to finance this work.

 

There is no impact to the General Fund.

 

A form of resolution has been approved by County Counsel.