COUNTY OF SAN MATEO

Inter-Departmental Correspondence

Department of Public Works

 

DATE:

October 4, 2004

BOARD MEETING DATE:

October 26, 2004

 

TO:

Honorable Board of Supervisors

FROM:

Neil R. Cullen, Director of Public Works

SUBJECT:

Memorial Park Electrical Distribution System Upgrades and Restroom Replacement Project

 

Recommendation

Adopt a resolution awarding and authorizing execution of a contract for electrical distribution system upgrades and the replacement of two restrooms in Memorial Park.

 

Previous Board Action

1.

Adopted Resolution No. 066839 on July 27, 2004, adopting plans and specifications, determining prevailing wage scales, and calling for sealed proposals for the above referenced project (Project).

 

2.

Adopted Resolution No. 066899 on August 31, 2004, rejecting the one bid received and authorizing the Director of Public Works to re-advertise for bids for the Project.

 

Key Facts

The Parks Division of the Environmental Services Agency has confirmed that there are sufficient grant and insurance funds available to finance the proposed work, based on the low bidder’s cost proposal and including contingencies.

 

Discussion

On September 30, 2004, bids were accepted for this project and subsequently referred to this office for checking and recommendation. The bids have been checked and the bid of:

 

Johnson Mechanical Contractors

9833 Kent Street / P.O. Box 404

Elk Grove, CA 95624 / 95759

 

at $439,538 was the lowest bid received.

 

The Engineer’s estimate was $475,000. A summary of the bids received is as follows:

 
 

1.

Johnson Mechanical Contractors

$439,538.00

 
 

2.

Columbia Electric Inc.

$519,937.50

 
 

3.

LEGG, Inc.

$549,000.00

 
 

4.

Zolman Construction & Development, Inc.

$601,925.00

 
 

We have reviewed the contract documents and have determined that the affirmative action program of Johnson Mechanical Contractors is in accordance with the current Affirmative Action Guidelines.

 

Vision Alignment

We believe our recommendation is consistent with Goal Number 7, “maintain and enhance the public safety of all residents and visitors,” of the Shared Vision Commitment to “ensure basic health and safety for all,” as the project is part of an overall program to maintain park facilities for the benefit of the public.

 

Fiscal Impact

The total estimated cost of construction is $483,500, which includes a contingency of $43,962 (approximately ten percent (10%) of the project costs) as the work is bid on a unit price basis (i.e., per linear foot for conduit, per cubic yard for concrete encasement, etc.). The contingency is used to pay the contractor for any additional material placed for the various bid items, based on the actual quantities used to complete the project.

 

The project is proposed to be financed as follows:

 
 

Proposition 12 Grant

$ 453,000

 
 

Risk Management (insurance funds related to bathroom destroyed by a tree)


$ 30,500

 
 

Total

$483,500

 
 

An appropriation in the Capital Projects Fund for the project has been included in the September budget revision.

 

There is no impact to the General Fund.

 

A form of resolution has been approved by County Counsel.