REVISION ORDER
Project: San Mateo County Youth Services Center |
Project No. P7T01 |
San Mateo County, California |
Revision Order No. 10 |
Contract Resolution No. 065620 |
Vendor: TURNER CONSTRUCTION COMPANY
________________________________________________________________
As provided by the terms of the Agreement, this Revision Order constitutes full and final adjustment of the Contract Amount and Contract Time in compensation for the changes to the Agreement and/or Project described herein. No claim for time or money relating to this Revision Order or the impact of changes on the Project will be allowed after execution of this document. Unchanged portions of the Agreement remain in full force and effect.
________________________________________________________________
Changes: See attached Revision Order Breakdown, which is incorporated herein as if fully set forth.
Contract Summary: |
|
Original Contract Amount |
$13,831,314 |
Prior Revisions |
$68,666,135 |
Net Amount Prior to This Revision |
$82,497,449 |
THIS REVISION ORDER |
$ 6,135,778 |
Revised Contract Amount |
$88,633,227 |
This Revision Order adds 0 days to the contract time. The revised substantial completion date of construction is March 6, 2006.
The revised contract completion date is December 3, 2006.
Approvals:
VENDOR: TURNER CONSTRUCTION COMPANY |
OWNER: COUNTY OF SAN MATEO | |
Signed by:_____________________________ |
Signed by: ___________________________ | |
Date:___________________________ |
Date:__________________________ |