SECOND AMENDMENT TO AGREEMENT

WITH G. E. CHEN CONSTRUCTION, INC. FOR

THE NOISE INSULATION PROJECT IN THE FOURTH QUARTER 1999 STATE

65 dB CNEL NOISE CONTOUR

 
 
 

THIS SECOND AMENDMENT TO THE AGREEMENT, entered into on this __________________ day of ____________, 2005, by and between the COUNTY OF SAN MATEO, hereinafter called “County,” and G. E. Chen Construction , Inc., hereinafter called “Contractor”;

 
 

W I T N E S S E T H:

 
 

WHEREAS, pursuant to Government Code, Section 31000, County may contract with independent contractors for the furnishing of such services to or for County or any Department thereof; and

 
 

WHEREAS, the parties entered into an Agreement for construction services to sound insulate five participating houses for the County of San Mateo Noise Insulation Project within the Fourth Quarter 1999 State 65 dB noise contour on March 11, 2003; and

 

WHEREAS, this Agreement was amended on March 29, 2005 to increase the contract amount by $11,812 to cover the increase in the cost of building materials since the award of the contract; and

 

WHEREAS, the parties wish to amend the Agreement to extend the term to allow for the delay caused by the re-fabrication of windows that did not meet the required acoustical rating for installation in the eligible properties.

 
 

NOW, THEREFORE, IT IS HEREBY AGREED BY THE PARTIES HERETO AS FOLLOWS:

 

1.

Section 6 of the Agreement is amended as follows:

The time of completion for this agreement and all work shall be three hundred (300) consecutive calendar days after the issuance of the Notice to Proceed, until February 8, 2006.

   

2.

All other terms and conditions of the Agreement dated March 11, 2003 and amended on March 29, 2005 between the County and Contractor shall remain the same and in full force and effect.

   

IN WITNESS WHEREOF, the parties hereto, by their duly authorized representatives, have affixed their hands.

 
 
 
 
 
 

COUNTY OF SAN MATEO

   
   
   
   
 

By:

 
   

Richard S. Gordon

President, Board of Supervisors

San Mateo County

   
 

Date:

 
   

ATTEST:

 
   
   
   
   

Clerk of Said Board

 
   

Date:

   
   
 

G. E. Chen Construction, Inc.

   
   
   
 

Name, Title – Print

   
   
   
 

Signature

   
 

Date:

 
   

BOS Contract Amend.dot