COUNTY OF SAN MATEO

Inter-Departmental Correspondence

Department of Public Works

 

DATE:

March 4, 2005

BOARD MEETING DATE:

March 29, 2005

SPECIAL NOTICE/HEARING:

None

VOTE REQUIRED:

Majority

 

TO:

Honorable Board of Supervisors

FROM:

Neil R. Cullen, Director of Public Works

SUBJECT:

Reconstruction of Portions of Camino de los Robles and Barney Avenue – West Menlo Park Area (Project No. RC500, RA700, F-36 [140A])

 

Recommendation

Adopt a Resolution adopting plans and specifications, determining prevailing wage scales, and calling for sealed proposals for the reconstruction of portions of Camino de los Robles and Barney Avenue.

 

Vision Alignment

Commitment: Ensure basic health and safety of all.

Goal(s): Maintain and enhance the public safety of all residents and visitors.

 

The reconstruction of these two streets will improve the condition of these roads for the benefit of the public.

 

Background

Previous Board Action

1.

Adopted resolutions establishing minimum road standards and a priority list for road improvements in the West Menlo Park Area.

   

2.

Adopted procedures to be used by Public Works to determine if property owners want minimum road improvements built on a specific street and the minimum road standard to be used in the design of the road improvements.

   

3.

Adopted a resolution directing the Department of Public Works to prepare design plans for the reconstruction of Barney Avenue between Camino a los Cerros and Valparaiso Avenue, and Camino de los Robles between Altschul Avenue and Alameda de las Pulgas.

 

4.

Authorized the Director of Public Works to execute agreements with cities, utility companies and special districts for work less than $50,000 proposed to be done in conjunction with County road projects.

 

History

Barney Avenue between Camino al Lago and Valparaiso Avenue, and Camino de los Robles between Altschul Avenue and Alameda de las Pulgas, are the next two streets on the West Menlo Park road priority list adopted by your Board that are proposed for reconstruction.

 

The street segments to be reconstructed and the standards to be used were based on the results of property owner surveys, and your Board subsequently authorized the Department to proceed with the design work.

 

Discussion

Plans and specifications for the work have now been prepared.

 

The San Mateo County Planning Department has determined that this project is exempt from the requirements for preparation of an EIR under Section 15301, Class 1, of the California Environmental Quality Act (CEQA), and we have filed a Notice of Exemption with the County Clerk.

 

We are now recommending that your Board authorize calling for bids for the proposed work.

 

A resolution has been approved as to form by County Counsel.

 

Fiscal Impact

The estimated cost of construction is $353,000 and is proposed to be financed as follows:

 
 

County Road Fund

$148,000

 
 

Roadway Improvement Fund (Mitigation Fees)

$200,000

 
 

West Bay Sanitary District

$ 5,000

 
 
 

Total Estimated Cost

$353,000

 
 

Reimbursement for the cost of doing work for the West Bay Sanitary District will be covered by an agreement executed by the Director as authorized by your Board.

 

Funds have been appropriated in both the Road Fund and Roadway Improvement Fund to finance this work.

 

There is no impact to the General Fund.