COUNTY OF SAN MATEO

Inter-Departmental Correspondence

Department of Public Works

 

DATE:

April 21, 2005

BOARD MEETING DATE:

May 3, 2005

SPECIAL NOTICE/HEARING:

None

VOTE REQUIRED:

Majority

 

TO:

Honorable Board of Supervisors

FROM:

Neil R. Cullen, Director of Public Works

SUBJECT:

Reconstruction of Portions of Camino De Los Robles and Barney Avenue – West Menlo Park Area (Project No. RA700, RC500, F-36 [140A])

 

Recommendation

Adopt a resolution awarding and authorizing execution of a contract for the reconstruction of portions of Camino De Los Robles and Barney Avenue.

 

Vision Alignment

Commitment: Ensure basic health and safety for all.

Goal(s): Maintain and enhance the public safety of all residents and visitors.

 

The reconstruction of these two streets will improve the condition of these roads for the benefit of the public.

 

Background

Previous Board Action

1.

Adopted Resolution No. 067231 on March 29, 2005, which adopted plans and specifications, determined prevailing wage scales and called for sealed proposals for the above-mentioned project.

   

2.

Authorized the Director of Public Works to execute agreements with utility agencies for utility type work costing less than $50,000 proposed to be done in conjunction with road projects.

 

History

On Tuesday, April 19, 2005, bids were accepted for this project and subsequently referred to this office for checking and recommendation.

 

Discussion

The bids have been checked and the bid of:

 

Half Moon Bay Grading & Paving, Inc.

1780 Higgins Canyon Road

Half Moon Bay, CA 94019-2522

 

at $323,394.00 was the lowest bid received.

 

The Engineer’s estimate was $353,000. A summary of the bids received is as follows:

 
 

1.

Half Moon Bay Grading & Paving, Inc.

$323,394.00

 
 

2.

G. Bortolotto & Co., Inc.

$353,149.51

 
 

3.

O’Grady Paving, Inc.

$373,887.00

 
 

4.

Interstate Grading & Paving, Inc.

$436,580.80

 
 

5.

Graniterock dba Pavex Construction Division

$473,273.00

 
 

6.

C.F. Archibald Paving, Inc.

$576,284.00

 
 

We have reviewed the Contract documents and have determined that the Equal Employment (Affirmative Action) program submitted by Half Moon Bay Grading & Paving, Inc. is in accordance with the current Equal Employment Guidelines.

 

Reimbursement for the cost of doing work for the West Bay Sanitary District will be covered by an agreement executed by the Director as authorized by your Board.

 

A resolution has been approved as to form by County Counsel.

 

Fiscal Impact

The total estimated cost for construction is $355,700, which includes a ten percent (10%) contingency (approximately $32,300) as the work is bid on a unit price basis (i.e., tons of asphalt concrete placed, cubic yards of concrete installed). The contingency is used to pay the contractor for any additional material placed for the various bid items as the actual quantity used depends on the unit weight and actual limits of the construction project.

 

The project is proposed to be financed as follows:

 
 

County Road Fund

$150,530.00

 
 

Roadway Improvement Fund (Mitigation Fees)

$200,000.00

 
 

West Bay Sanitary District

$5,170.00

 
 

Total Estimated Cost

$355,700.00

 
 

Funds have been appropriated in the Road Fund and the Roadway Improvement Fund to finance this project.

 

There is no impact to the General Fund.