REVISION ORDER

Project: Youth Services Center

Project No. P7T01

 

San Mateo County, California

Contract Resolution No. 065620

 

Revision Order No. 20

   

Vendor: TURNER CONSTRUCTION COMPANY

Contract: 36

 

________________________________________________________________

As provided by the terms of the Agreement, this Revision Order constitutes full and final adjustment of the Contract Amount and Contract Time in compensation for the changes to the Agreement described herein. No claim for time or money relating to this Revision Order or the impact of changes on the Project will be allowed after execution of this document. Unchanged portions of the Agreement remain in full force and effect.

 

________________________________________________________________

 

Changes: See attached Revision Order Breakdown, which is incorporated herein as if fully set forth.

 

Contract Summary:

   
     

Original Contract Amount

$13,831,314

 

Prior Revisions

109,102,154

 

Net Amount Prior to This Revision

122,933,468

 

THIS REVISION ORDER

1,700,184

 

Revised Contract Amount

124,633,652

 
   

This Revision Order adds 0 days to the contract time. The revised substantial completion date of construction is March 6, 2006.

The revised contract completion date is December 3, 2006.

 

Approvals:

 

VENDOR:

TURNER CONSTRUCTION COMPANY

 

OWNER:

COUNTY OF SAN MATEO

Signed by:_____________________________

 

Signed

by: ___________________________

Date:___________________________

 

Date:__________________________