COUNTY OF SAN MATEO

Inter-Departmental Correspondence

Department of Public Works

 

DATE:

April 10, 2006

BOARD MEETING DATE:

April 18, 2006

SPECIAL NOTICE/HEARING:

None

VOTE REQUIRED:

Majority

 

TO:

Honorable Board of Supervisors

FROM:

Neil R. Cullen, Director of Public Works

SUBJECT:

Reconstruction of a Portion of Ninth Avenue – North Fair Oaks Area (Project No. RD100, F-36 [305-1B])

 

Recommendation

Adopt a resolution awarding and authorizing execution of a contract for the reconstruction of a portion of Ninth Avenue.

 

Vision Alignment

Commitment: Ensure basic health and safety for all.

Goal(s): Maintain and enhance the public safety of all residents and visitors.

 

The reconstruction of this street will improve the condition of the road for the benefit of the public.

 

Background

 

Previous Board Action

1.

Adopted resolutions establishing minimum road standards and a priority list for road improvements in the North Fair Oaks Area.

   

2.

Authorized the Director of Public Works to re-advertise the project for bids after the initial low bidder was relieved of their bid due to errors, and the other bids were rejected.

 

3.

Authorized the Director of Public Works to execute agreements with utility agencies for utility type work costing less than $50,000 proposed to be done in conjunction with road projects.

 

History

Ninth Avenue between Oak Drive and Edison Way is the next street on the North Fair Oaks road reconstruction priority list approved by your Board. Bids for the project were accepted on Tuesday, April 4, 2006, and subsequently referred to this office for checking and recommendation.

 

Discussion

The bids have been checked and the bid of:

 

Interstate Grading and Paving, Inc.

128 South Maple Avenue

South San Francisco, CA 94080

 

at $366,242 was the only bid received. The Engineer’s estimate was $347,000.

 

We have reviewed the Contract prices submitted by Interstate Grading and Paving, Inc. (Interstate) and believe that they are reasonable. It is our recommendation that Interstate be awarded the Contract for this project.

 

We have also reviewed the Contract documents and have determined that the Equal Employment (Affirmative Action) program submitted by Interstate is in accordance with the current Equal Employment Guidelines; and have also determined that Interstate complies with the equal benefits and jury duty pay provisions of the County ordinance code.

 

A resolution has been approved as to form by County Counsel.

 

Fiscal Impact

The total estimated cost for construction is $402,850, which includes a ten percent (10%) contingency (approximately $36,608) as the work is bid on a unit price basis (i.e., tons of asphalt concrete placed, cubic yards of concrete installed). The contingency is used to pay the contractor for any additional material placed for the various bid items, as the actual quantity used depends on the unit weight and actual limits of the construction project.

 

The project is proposed to be financed as follows:

 
 

County Road Fund

$246,450

 
 

Roadway Improvement Fund (Mitigation Fees)

$150,000

 
 

Fair Oaks Sewer Maintenance District

$4,650

 
 

California Water Service Company

$1,750

 
 

Total Estimated Cost

$402,850

 
 

Funds have been appropriated in both the Road Fund and the Roadway Improvement Fund to finance this work.

 

Reimbursement for the cost of doing work for the Fair Oaks Sewer Maintenance District and the California Water Service Company will be covered by agreements executed by the Director as authorized by your Board.

 

There is no impact to the General Fund.