COUNTY OF SAN MATEO

Inter-Departmental Correspondence

Department of Parks

 

DATE:

May 30, 2007

BOARD MEETING DATE:

June 19, 2007

SPECIAL NOTICE/HEARING:

Ten-day Notice

Public Hearing

VOTE REQUIRED:

Majority

 

TO:

Honorable Board of Supervisors

FROM:

David H. Holland, Director, Department of Parks

SUBJECT:

Amend Selected Park and Marina Berthing Fee Schedules

 

RECOMMENDATION:

Adopt a Resolution amending selected Park and Marina Berthing Fee Schedules.

 

VISION ALIGNMENT:

Commitment: Responsive, effective and collaborative government.

Goals) 20 and 24: Government decisions are based on careful consideration of future impact, rather than temporary relief or immediate gain. Residents accept individual responsibility for contributing to the quality of life of the County as a whole.

 

The proposed fee changes contribute to the commitment and goals by maintaining a proper relationship between costs and revenues and by assuring that those who utilize County services pay the cost of providing those services, rather than receiving a subsidy from taxpayers and thereby diverting resources from other needed programs without a source of cost recovery.

 

BACKGROUND:

Periodically, Parks Department staff reviews the fees charged for use of the parks, park features and park services and looks at facility usage, operational costs, changes in the cost of living index and market rate comparisons.

 

Annually, Parks Department staff looks at Marina berth rental fees as the County’s loan agreement with the California Department of Boating and Waterways requires that the Coyote Point Marina berth rental fees be adjusted annually by a rate not less than the local Consumer Price Index (CPI). In general, fees are increased to first meet the legal minimum, and then to provide adequate funding for the Marina’s capital projects. Marina staff conducts a survey of competing facilities to ensure the County’s fees continue to be in line with the market. These fees are accumulated in the Marina enterprise fund, separate from the County General Fund.

 

DISCUSSION:

Based on market rate comparisons and increased costs, staff is recommending fee increases to the general user fees for the two small areas of the Jack Brook Horse Camp, baseball field practice and game fees for adult leagues and youth and school leagues, firewood fees, maintenance fees, filming and photography fees, and the reservation change fee. Staff also recommends changing the Reservation Fee Refund Policy to make reservations for all three Toyon Campgrounds non-refundable and non-changeable similar to the no refund, no change policy currently in place for Jack Brook Horse Camp, Wurr Flat Group Campsites, and the Baseball Fields.

In accordance with state law, the resulting fees would not exceed the cost of providing services. If the fees were approved, they would become effective July 1, 2007.

Marina berth rental fees are recommended to increase by 2.4% and if approved, would become effective August 1, 2007. This is within the parameters required by the loan agreements and is sufficient to support the annual cost of maintenance and operation as well as maintain adequate reserves for long-term capital improvement projects and the depreciation of the entire Marina facility. These rates are competitive with the local market and are not expected to decrease berth occupancy.

The Park and Recreation Commission at their April 5, 2007 regular meeting reviewed the proposed fee changes and unanimously voted to recommend that the Board adopt a resolution authorizing the amendment of the selected Park and Marina fee schedules. The fee schedules that summarize the changes for the Park and Marina fees are part of the resolution.

 

FISCAL IMPACT:

If the Park’s fee changes are adopted, the Department anticipates receiving $3,700 additional parks revenue that will offset cost increases in the Department’s expenditure budget. If the Marina berth rental fees are adopted, the estimated increase in revenue would be approximately $24,500. This estimate is based on the current level of berth occupancy, which is down due to the dredging project. If berth occupancy increases as anticipated, the total increase in revenue will be greater.