RESOLVED, by the Board of Supervisors of the County of San Mateo, State of California, as the governing board of the following Sewer Maintenance and County Sanitation Districts (Districts):
|
|
Burlingame Hills Sewer Maintenance District;
|
Crystal Springs County Sanitation District;
|
Devonshire County Sanitation District;
|
Edgewood Sewer Maintenance District;
|
Emerald Lake Heights Sewer Maintenance District;
|
Fair Oaks Sewer Maintenance District;
|
Harbor Industrial Sewer Maintenance District;
|
Kensington Square Sewer Maintenance District;
|
Oak Knoll Sewer Maintenance District;
|
Scenic Heights County Sanitation District.
|
|
WHEREAS, the Districts own, operate, and maintain approximately 150 miles of sanitary sewer pipelines; and
|
|
WHEREAS, it is the Districts’ responsibility to effectively manage the sewer systems to minimize sanitary sewer overflows (SSOs); and
|
|
WHEREAS, the State of California Water Resources Control Board has adopted statewide General Waste Discharge Requirements for sanitary sewer systems, Water Quality Order No. 2006-0003 (Order) to provide a consistent, statewide regulatory approach to address SSOs; and
|
|
WHEREAS, the Order requires the development of a Sewer System Management Plan (SSMP) and schedule by all public agencies that own or operate sanitary sewer systems greater than one mile in length that collect and/or convey wastewater to a publicly owned treatment facility; and
|
|
WHEREAS, the Order requires that the governing board of each sanitary sewer system approve the development of a SSMP and development schedule at a public meeting; and
|
|
NOW THEREFORE, IT IS HEREBY DETERMINED AND ORDERED that acting as the governing board of the Districts, that this Board approves the development of a Sewer System Management Plan and schedule as shown below:
|
|
|
Tasks Specified in GWDR
|
Required Completion Dates
|
|
|
Present SSMP Development Plan and Schedule to the Governing Board
|
November 2, 2007
|
|
|
Develop Elements of SSMP:
|
|
|
1.
|
Goal
|
|
|
2.
|
Organization
|
|
|
3.
|
Legal Authority
|
May 2, 2009
|
|
|
4.
|
Operation and Maintenance Program
|
|
|
5.
|
Overflow Emergency Response Plan
|
|
|
6.
|
Fats, Oils, and Grease (FOG) Control Program
|
|
|
7.
|
Design and Performance Provisions
|
August 2, 2009
|
|
|
8.
|
System Evaluation and Capacity Assurance Plan
|
|
|
9.
|
Monitoring, Measurement, and Program Modifications
|
|
|
10.
|
SSMP Program Audits
|
|
|
11.
|
Communication Program
|
|
|
Present Final SSMP to the Governing Board
|
|
|
* * * * * *
|