COUNTY OF SAN MATEO

Inter-Departmental Correspondence

 

PLANNING AND BUILDING DEPARTMENT

 

DATE:

September 25, 2008

BOARD MEETING DATE:

October 7, 2008

SPECIAL NOTICE/HEARING:

300 feet

VOTE REQUIRED:

Majority

 
 

TO:

Honorable Board of Supervisors

 

FROM:

Lisa Grote, Director of Community Development

 

SUBJECT:

Consideration of an “After-the-Fact” Coastal Development Permit, pursuant to Section 6328 of the San Mateo County Zoning Regulations, to allow the construction of a fence. The project also includes site restoration, which includes 250 cubic yards of excavation. The project site is located diagonally across Date Street along the edge of the State Highway 1 bypass right-of-way, in the unincorporated Montara area of San Mateo County. This project is appealable to the California Coastal Commission. (Appeal of the Planning Commission’s decision for approval.)

 
 

County File Number:

PLN 2007-00277 (CalTrans)

 

RECOMMENDATION

 

Deny the appeal and uphold the Planning Commission’s decision to approve the Coastal Development Permit subject to the conditions imposed by the Planning Commission.

   

VISION ALIGNMENT

 

Commitment: The proposed project keeps the commitment of “Preserving and providing people access to our natural environment” by removing the chain link fence preserving the open space character of the subject area.

 

Goal Number: The proposed project achieves Goal Number 14: “Important natural resources are preserved and enhanced through environmental stewardship.” This proposal contributes to this commitment and goal by requiring revegetation of the site with native plant species and installation of rock bollards and/or other natural appearing bollards to restore and preserve the site, thereby enhancing natural resources.

 

PROPOSAL

 

The applicant applied for an “After-the-Fact” Coastal Development Permit (in response to VIO 2007-00048) for the construction of a 210-foot long, 6-foot high chain link fence along the property line adjacent to 932 Date Street to prevent trespassing and unauthorized activities occurring on State-owned property. Subsequent to the application, approximately half of the fence has been removed and a site restoration plan for a 10,000 sq. ft. area has been submitted.

 

BACKGROUND

 

Report Prepared By: Melissa Ross, Project Planner, Telephone 650/599-1559

 

Appellant: CalTrans

 

Applicant/Owner: CalTrans

 

Location: Public right-of-way: Highway 1 Bypass adjacent to 932 Date Street, Montara

 

Existing Zoning: R-1/S-17/DR/CD

 

General Plan Designation: Medium Density Residential (6.1 – 8.7 density units/acre)

 

Existing Land Use: Unimproved CalTrans right-of-way

 

Flood Zone: FEMA Flood Insurance Rate Map Zone C (Area of Minimal Flooding); Community Panel No. 060311 0111 B; effective date: July 5, 1984.

 

Environmental Evaluation: CalTrans, as lead agency, has prepared a Categorical Exemption/Categorical Exclusion Determination and determined this project to be Categorically Exempt under Section 15301 of the California Environmental Quality Act (see Attachment D).

 

Setting: To the north of the project site are single-family residences and the continuation of the Highway 1 bypass lands; to the south and west are single-family residences. To the east of the project site are single-family residences as well as agricultural land. At the southern end of the existing fence is a fire truck turnaround. Ground vegetation in the area has been degraded due to vehicle parking and the use of the property as a staging area for construction vehicles and materials. A number of trees show signs of lower limb removal.

 

Chronology: On March 5, 2007, a violation for construction of a 6-foot high chain link fence without a Coastal Development Permit was submitted. On July 11, 2007, an application for an “After-the-Fact” Coastal Development Permit was submitted for construction of the 210-foot long, 6-foot high fence. The Planning Commission public hearing was held on June 25, 2008, and the Coastal Development Permit was approved with modified conditions of approval. On July 9, 2008, the applicant, CalTrans, filed an appeal of the Planning Commission’s approval.

 

DISCUSSION

 

A.

PREVIOUS ACTION

     
 

As approved by the Planning Commission, the restoration plan includes:

     
 

1.

the removal of approximately 250 cubic yards of fill material, 18 inches in depth, to return a 5,000 sq. ft. area to original grade,

     
 

2.

debris removal within a 5,000 sq. ft. area, and

     
 

3.

planting or seeding the site with native plants.

     
 

In approving the Coastal Development Permit on June 25, 2008, the Planning Commission modified the proposed conditions of approval, resulting in modifications to the proposed project for compliance with Local Coastal Program policies. Specifically, the conditions approved by the Planning Commission include removal of the existing chain link fence the day following the end of the appeal period, prohibiting the use of an Environmentally Sensitive Area (ESA) fence to surround the site proposed for revegetation, a reduction in the amount of proposed rock bollards and/or the use of other natural appearing bollards, and the addition of a tree protection zone condition during site restoration activities.

     
 

On July 9, 2008, the applicant, CalTrans, filed an appeal of the Planning Commission’s modified conditions of approval imposed on the approval which include the removal of the chain link fence on the day following the end of the appeal period and prohibiting the use of an Environmentally Sensitive Area fence surrounding the restoration site. The appellant also raised concerns that the Planning Commission either misunderstood or failed to appreciate the purpose and reasons for installing the chain link fence and maintaining the chain link fence during restoration.

   
 

The applicant stated the installation of the chain link fence is to prevent unauthorized parties from trespassing onto State property in response to vehicles and construction related equipment and materials encroaching onto the CalTrans’ right-of-way and that the removal of the chain link fence inhibits successful restoration of the site.

   
 

Staff recommends that the removal of the chain link fence and implementation of the restoration plan as conditioned by the Planning Commission complies with the Local Coastal Program Visual Resources Component.

     

B.

KEY ISSUES OF THE APPEAL

   
 

The appellant’s basis for appeal of the decision is described below, followed by staff’s response. A copy of the appellant’s appeal is included as Attachment C of this report.

   
 

1.

The Planning Commission made an unreasonable condition ordering removal of the fence by July 11, 2008, at 5:00 p.m.

     
   

Recommended Condition: The existing chain link fence shall be removed, in its entirety, within one year while site restoration occurs, from the date of this permit approval and said removal verified during the staff level administrative review.

     
   

Modified Condition: The existing chain link fence shall be removed in its entirety by 5:00 p.m. on July 11, 2008 (the eleventh working day following this approval).

     
   

Staff’s Response: Staff originally proposed removal of the fence within one year to protect the site during restoration since the applicant’s restoration plan did not indicate if or when the fence would be removed. The Planning Commission modified this condition to require removal immediately following the end of the appeal period. The Planning Commission found the fence not to be in compliance with the Local Coastal Program Visual Resource Policies. Staff agrees with the Planning Commission in that the chain link fence does not comply with Local Coastal Program policies. Staff has modified the condition to require removal of the fence within a week of the Board’s decision. See Condition No. 6 in Attachment A.

     
 

2.

The Planning Commission either misunderstood or failed to appreciate the purpose and reasons for installing and maintaining a fence during restoration.

     
   

Staff’s Response: In reaching its decision, the Planning Commission reviewed staff’s report on this matter and took testimony from the public, including the applicant before rendering a decision. The applicant has stated the purpose of the chain link fence is to prevent unauthorized trespass and activities on State-owned property by non-State personnel and had agreed to remove it within one year of approval. The Commission was aware of the reasons cited by CalTrans for the fence but determined, on balance, to modify the conditions of approval for the Coastal Development Permit, to require removal of the fence.

     
 

3.

The State’s fiscal year began without a budget, limiting the State’s ability to comply with conditions of the permit.

     
   

Staff’s Response: All actions required by the Planning Commission’s decision are pending, subject to completion of this appeal process.

     
 

4.

The Planning Commission’s decision delivers a purely private benefit on the perpetrators of the illegal and unauthorized encroachment, while the State’s proposal benefits the community at large.

     
   

Staff’s Response: The Planning Commission’s responsibility is to review the project as proposed, consider public comments and assure compliance with Local Coastal Program policies which seek to benefit the community at large.

     
 

5.

From a practical standpoint, installing the bollards prior to restoration severely inhibits the ability to excavate alien fill and gravel.

     
   

Staff’s Response: The conditions of approval do not require the installation of the rock bollards prior to excavation.

     
 

6.

In its discussion of the rock bollards, the Planning Commission appeared to request the bollards be buried up to 24 inches deep, leaving 12 inches of the bollard above grade. This defeats the purpose of the rock bollards – to prevent vehicle traffic from entering the State’s right-of-way.

     
   

Staff’s Response: Staff originally proposed the following condition: This approval allows for the installation of 23 two-ton rock bollards (dimensions of 3’ x 3’ x 3’) as depicted in the restoration plan. The rock bollards shall be partially buried a minimum 1/3 of the bollards’ height. The Planning Commission modified the condition to read: …a maximum of 1/2 to 1/3 of each rock bollard shall be exposed, not to exceed 18 inches above grade (see Attachment B for full text).

     
   

The condition, as approved by the Planning Commission, limits the above ground rock bollard height to 18 inches. Because the ground clearance for most vehicles is less than 18 inches, staff believes that 18 inches above grade is sufficient to deter vehicle access to the restoration site.

     
 

7.

The conditions of the permit are inherently inconsistent: the Planning Commission denied the State a temporary, 4-foot high, orange, Environmentally Sensitive Area fence around the restoration area because of looks, yet required the same fence be placed around existing tree driplines.

     
   

Staff’s Response: The addition of a tree protection zone and the inclusion of the 4-foot high, orange fencing around the dripline of existing trees is meant to protect the trees during site excavation activities in which the time frame for completion is considerably less than successfully establishing vegetation in the restoration area.

     
   

In modifying the proposed conditions, the Planning Commission made the determination that the placement of the orange ESA fence around the site for an indeterminate period of time would conflict with the Local Coastal Program Visual Resource Policies.

     

C.

ALTERNATIVES

     
 

1.

Alternative A

     
   

Deny the appeal and uphold the Planning Commission’s findings and conditions of approval dated June 25, 2008 (Attachment B).

     
 

2.

Alternative B

     
   

Grant the appeal subject to the findings and conditions of approval recommended by staff to the Planning Commission on June 25, 2008 (Attachment D).

     
 

3.

Alternative C

     
   

Grant the appeal subject to modified conditions of approval. The following modified conditions of approval are offered as a way to balance staff’s recommendations presented on June 25, 2008, and the Planning Commission’s conditions of approval.

     
   

a.

Condition No. 8

       
     

Staff’s recommendation for this condition on June 25, 2008, recommended the removal of the chain link fence within one year to provide protection to the reseeded and revegetated area. The Planning Commission’s decision called for the immediate removal of the chain link fence and the removal of the Environmentally Sensitive Area fence from the restoration plan.

       
     

Modified Condition No. 8: Reinstate the 4-foot high Environmentally Sensitive Area (ESA) fence in the restoration plan and amend the condition to include the removal of the ESA fence after six months, from the date of final approval, to protect the reseeded and revegetated area.

       
   

b.

Condition No. 5

       
     

Amend Condition No. 5 to modify the administrative review from one year to six months from the date of final approval to coincide with the removal of the ESA fence.

       

D.

ENVIRONMENTAL REVIEW

     
 

CalTrans, as lead agency, has prepared a Categorical Exemption/Categorical Exclusion Determination and determined this project to be Categorically Exempt under Section 15301 of the California Environmental Quality Act.

     

E.

REVIEWING AGENCIES

     
 

County Counsel

     

FISCAL IMPACT

     

No net change.

     

ATTACHMENTS

     

A.

Recommended Findings and Conditions of Approval

B.

Letter of Decision dated June 27, 2008

C.

Appeal Form dated July 9, 2008

D.

Staff Report Including Documentation dated June 25, 2008

   

Attachment A

 

COUNTY OF SAN MATEO

PLANNING AND BUILDING DEPARTMENT

 

RECOMMENDED FINDINGS AND CONDITIONS OF APPROVAL

 

Permit File Number: PLN 2007-00277

Board Meeting Date: October 7, 2008

 

Prepared By: Melissa Ross

For Adoption By: Board of Supervisors

 
 

RECOMMENDED FINDINGS

 

1.

For the Environmental Review, Find:

   
 

That the Board, acting as a responsible agency, has reviewed and considered the Categorical Exemption/Categorical Exclusion Determination, prepared by CalTrans as lead agency.

 

2.

For the Coastal Development Permit, Find:

     
 

a.

That this project, as described in the application and accompanying materials required by Section 6328.7, and as conditioned in accordance with Section 6328.14, conforms with the plans, policies, requirements and standards of the San Mateo County Local Coastal Program.

     
 

b.

That the project conforms to specific findings required by the policies of the San Mateo County Local Coastal Program.

   

RECOMMENDED CONDITIONS OF APPROVAL

 

1.

This approval applies only to the proposal, documents and plans described in this report and submitted to, approved, and modified by the Board of Supervisors on October 7, 2008. Minor revisions or modifications may be approved by the Community Development Director if they are consistent with the intent of and in substantial conformance with this approval.

   

2.

The Coastal Development Permit shall be valid for one year. Any extension of this permit shall require submittal of an application for permit extension and payment of applicable permit extension fees.

   

3.

The applicant shall submit a revised restoration plan, including elevations, to the Current Planning Section for review and approval. The restoration plan shall incorporate rock and/or other natural appearing bollards adjacent to the CalTrans property line with the minimum number of rock bollards to prevent vehicular access. Rock bollards shall be randomly placed in singles and clusters and varied in height. Each cluster shall be installed no greater than 3 feet apart (edge-to-edge), and a maximum of 1/2 to 1/3 of each rock bollard shall be exposed, not to exceed 18 inches above grade. Placement shall not be in a straight line parallel to the property line, but at random distances from said property line. Any bollards, other than rock, shall be proposed at the lowest possible height and greatest distance possible to prevent vehicular access. The applicant shall maintain all bollards.

   

4.

This approval does not allow for the installation of K-rail (concrete barriers).

   

5.

This Coastal Development Permit shall also be subject to an administrative review which shall occur no later than one year from the date of this permit approval. The purpose of the administrative review is to assure continued compliance with the conditions of approval. The administrative review shall be conducted at staff level, i.e., without a public hearing. However, should staff determine that the conditions of approval are not being met, that review shall be conducted at a public hearing by the Planning Commission.

   

6.

The existing chain link fence shall be removed in its entirety by 5:00 p.m. on October 14, 2008.

   

7.

The applicant shall restore the site as approved in the restoration plan. Site restoration shall be verified during the staff level administrative review.

   

8.

The approved restoration plan includes: (1) the removal of approximately 250 cubic yards of fill material, 18 inches in depth, to return a 5,000 sq. ft. area to original grade; (2) debris removal within a 5,000 sq. ft. area; and (3) planting or seeding the site with native plants. Any revisions or modifications to the above items may be approved by the Community Development Director upon written request and submittal of any applicable documents for review and consideration.

   

9.

This permit does not allow for the removal of any trees. Removal of any tree with a diameter equal to or greater than 12 inches as measured 4.5 feet above the ground shall require a separate tree removal permit.

   

10.

All existing significant and heritage trees shall be protected during all restoration activities. The applicant shall establish and maintain tree protection zones which shall be delineated using a 4-foot tall orange plastic fencing supported by poles pounded into the ground, located as close to the tree driplines as possible while still allowing room for restoration to safely continue. The applicant shall maintain tree protection zones free of equipment and material storage and shall not clean any equipment within these areas. Should any large roots or large masses of roots need to be cut, the roots shall be inspected by a certified arborist prior to cutting. Any root cutting shall be monitored by an arborist and documented.

   

11.

Prior to the beginning of any construction or grading activities, the applicant shall implement erosion and sediment control measures. Erosion control measure deficiencies, as they occur, shall be immediately corrected. The goal is to prevent sediment and other pollutants from leaving the project site and to protect all exposed earth surfaces from erosive forces. Said plan shall adhere to the San Mateo Countywide Stormwater Pollution Prevention Program “General Construction and Site Supervision Guidelines,” including:

   
 

a.

Stabilizing all denuded areas and maintaining erosion control measures continuously between October 15 and April 15. Stabilizing shall include both proactive measures, such as the placement of hay bales or coir netting, and passive measures, such as revegetating disturbed areas with plants propagated from seed collected in the immediate area.

     
 

b.

Storing, handling, and disposing of construction materials and wastes properly, so as to prevent their contact with stormwater.

     
 

c.

Controlling and preventing the discharge of all potential pollutants, including pavement cutting wastes, paints, concrete, petroleum products, chemicals, wash water or sediments, and non-stormwater discharges to storm drains and watercourses.

     
 

d.

Using sediment controls or filtration to remove sediment when dewatering the site and obtaining all necessary permits.

     
 

e.

Avoiding cleaning, fueling, or maintaining vehicles on-site, except in a designated area where wash water is contained and treated.

     
 

f.

Delineating with field markers clearing limits, easements, setbacks, sensitive or critical areas, buffer zones, trees, and drainage courses.

     
 

g.

Protecting adjacent properties and undisturbed areas from construction impacts using vegetative buffer strips, sediment barriers or filters, dikes, mulching, or other measures as appropriate.

     
 

h.

Performing clearing and earth-moving activities only during dry weather.

     
 

i.

Limiting and timing applications of pesticides and fertilizers to prevent polluted runoff.

     
 

j.

Limiting construction access routes and stabilizing designated access points.

     
 

k.

Avoiding tracking dirt or other materials off-site; cleaning off-site paved areas and sidewalks using dry sweeping methods.

     
 

l.

The contractor shall train and provide instructions to all employees and subcontractors regarding the construction best management practices.

     
 

m.

The approved erosion and sediment control plan shall be implemented prior to the beginning of construction.