RESOLUTION NO. _____________

BOARD OF SUPERVISORS, COUNTY OF SAN MATEO, STATE OF CALIFORNIA

* * * * * *

RESOLUTION INCREASING THE CONTRACT WITH STOLOSKI AND GONZALES, INC. BY $35,000 FOR A TOTAL CONTRACT AMOUNT OF $391,500 IN ORDER TO INCLUDE THE COST FOR WORK TO RELOCATE EXISTING MONTARA WATER AND SANITARY DISTRICT WATER MAINS THAT ARE IN CONFLICT WITH THE PROPOSED STORM DRAINAGE IMPROVEMENTS TO BE CONSTRUCTED FOR THE MIDCOAST DRAINAGE IMPROVEMENT PROJECT – CYPRESS AVENUE FROM HIGHWAY 1 TO ETHELDORE STREET, ETHELDORE STREET FROM SUNSHINE VALLEY ROAD TO VERMONT AVENUE, AND SUNSHINE VALLEY ROAD FROM STETSON STREET TO ETHELDORE STREET – MOSS BEACH AREA (PROJECTS NO. M0210, M0211, F-149[21])

______________________________________________________________

RESOLVED, by the Board of Supervisors of the County of San Mateo, State of California, that

 

WHEREAS, on July 22, 2008 the Board of Supervisors adopted Resolution No. 069601, approving revised plans and specifications, determining prevailing wage scales and authorizing execution of a contract with Stoloski & Gonzales, Inc., hereinafter referred to as “Contractor,” for the Midcoast Drainage Improvement Project; and

 

WHEREAS, the Director of Public Works has determined that the Montara Water & Sanitary District, hereinafter referred to as “District,” owns and operates water mains of which four (4) conflicts with the proposed storm drainage improvements exist; and

 

WHEREAS, the District water mains must be relocated before the Contractor can proceed with construction; and

 

WHEREAS, the Contractor has provided a cost proposal in the amount of $25,900 for performing the work to relocate the District water mains; and the District has agreed to the Contractor’s proposal and has executed a cost-sharing agreement with the County; and

 

WHEREAS, an increase in the Contract amount of $35,000 is required to cover the cost for the relocation work and any additional work necessitated by design changes to the storm drainage improvements; and

 

WHEREAS, the Board has considered and concurs with the recommendation of the Director of Public Works.

 

NOW THEREFORE, IT IS HEREBY DETERMINED AND ORDERED that:

 

The contract amount is hereby increased by $35,000, for a total contract Not-To-Exceed amount of $391,500.

* * * * * *