COUNTY OF SAN MATEO
Inter-Departmental Correspondence
|
Department of Public Works
|
|
DATE:
|
February 27, 2009
|
BOARD MEETING DATE:
|
March 31, 2009
|
SPECIAL NOTICE/HEARING:
|
None
|
VOTE REQUIRED:
|
Majority
|
|
TO:
|
Honorable Board of Supervisors
|
FROM:
|
James C. Porter, Director of Public Works
|
SUBJECT:
|
Maguire Correctional Facility Outdoor Recreation Deck Resurfacing, 300 Bradford Street, Redwood City (Project No. P9U03)
|
|
RECOMMENDATION:
|
Adopt a resolution adopting plans and specifications, including conformance with prevailing wage scale requirements, and calling for sealed bids on Tuesday, May 5, 2009, at 2:30 p.m. for Maguire Correctional Facility Outdoor Recreation Deck Resurfacing, 300 Bradford Street, Redwood City, California (Project No. P9U03).
|
|
VISION ALIGNMENT:
|
Commitment: Ensure basic health and safety for all.
|
Goal 7: Maintain and enhance the public safety of all residents and visitors.
|
|
Adoption of the proposed resolution contributes to this commitment and goal by sustaining a major building system for the benefit of the individuals housed at this facility.
|
|
BACKGROUND:
|
An appropriation to apply new waterproof coating to two outdoor recreation decks at this facility is included in the 2008-2009 Capital Projects Budget.
|
|
DISCUSSION:
|
The proposed project will provide new deck coating and wall flashing at a 4th floor outdoor recreation area as well as a smaller 2nd floor outdoor recreation area. Both areas currently leak during seasonal rains.
|
|
The resolution has been approved as to form by County Counsel.
|
|
FISCAL IMPACT:
|
The estimated construction cost is $150,000. An appropriation was established in the Capital Projects Budget that is financed by the County General Fund.
|