RESOLUTION NO. _____________
|
BOARD OF SUPERVISORS, COUNTY OF SAN MATEO, STATE OF CALIFORNIA
|
* * * * * *
|
RESOLUTION INCREASING THE PUBLIC WORKS DIRECTOR’S AUTHORITY TO EXECUTE CHANGE ORDERS TO THE AGREEMENT WITH SOIL ENGINEERING CONSTRUCTION, INC., TO INCREASE THE “NOT-TO-EXCEED” AMOUNT OF $287,550 BY AN ADDITIONAL $40,000, TO A NEW “NOT-TO-EXCEED” AMOUNT OF $327,550, IN ORDER TO ALLOW FOR PAYMENT OF UNANTICIPATED PROJECT COSTS RELATED TO THE SEAL COVE TRAIL IMPROVEMENT PROJECT – FITZGERALD MARINE RESERVE – MOSS BEACH AREA
|
______________________________________________________________
|
RESOLVED, by the Board of Supervisors of the County of San Mateo, State of California, that
|
|
WHEREAS, on November 10, 2009, the Board of Supervisors adopted Resolution No. 070517, which adopted plans and specifications, including conformance with prevailing wage rates scale requirements, approved filing of a CEQA Notice of Exemption, and called for sealed proposals for the Seal Cove Trail Improvement Project (Project); and
|
|
WHEREAS, on December 15, 2009 the Board of Supervisors adopted Resolution No. 070580, which awarded and authorized execution of a agreement with Soil Engineering Construction, Inc. for the Project with a not-to-exceed amount of $287,550, which included an agreement in the amount of $239,625 and the Director of Public Works’ authority to execute change orders in an amount not to exceed $47,925; and
|
|
WHEREAS, unforeseen conditions were encountered during construction and changes were required in order to address said conditions; and
|
|
WHEREAS, the dimensions of the concrete support piers were modified by increasing the diameter and length of piers as well as modifications to the bottom stairs were required as a result of the bluff erosion that had occurred subsequent to completion of the Project plans and specifications; and
|
|
WHEREAS, water intrusion into the construction site occurred, which required additional excavation and installation of rock to stabilize the site and direct water away from the piers and stairs; and
|
|
WHEREAS, additional grading adjacent to the stairwell was required to reduce the potential for slope erosion; and
|
|
WHEREAS, an increase in the agreement amount of $40,000 is required for the additional work necessitated by the unforeseen site conditions for the Project; and
|
|
WHEREAS, the Board has considered and concurs with the recommendation of the Director of Public Works.
|
|
NOW THEREFORE, IT IS HEREBY DETERMINED AND ORDERED that:
|
|
The Director of Public Works’ authority to execute change orders to the agreement with Soil Engineering Construction, Inc. is hereby increased by an additional amount of $40,000, to a new not-to-exceed amount of $327,550 in order to allow for the payment of unanticipated project costs related to the Seal Cove Trail Improvement Project.
|
* * * * * *
|